Hi Waseda-san
As of now, we have started to change the future demand forecast from D32612D12FAJV to D32612D17FAJV in the RB system.
Basically base on 16weeks leadtime to Flex/Schneider, we may need to start to support new part from July onwards but we need to bring in one month buffer stock in June as we have an agreement with Schneider
for some items.
So we need your support to inform us to check the liability stocks for D32612D12FAJV as of now so that we can request Schneider to clear off all the stocks before they change to D32612D17FAJV .
Hope to hear from you soon.