Dear Katsumata San,
Good Morning!!!
With reference to your below mail, regarding the cost merit for the CRF. Please note the following.
Current Situation:
1. This CRF was raised by QD member and was not discussed by New Model (Rahul San or Vinay). Yesterday was first time information for us.
2. Since the time was very short (only 2 days) for the drawing issue for the tooling go, so as per the agreement between HGID & HCIL Pur PIC "TBD" was written in cost estimate area.
3. HGID estimate was written at the comments area for HGID and actual cost verification will be done at V3 seigou timing.
Proposal:
1. Based on the discussion it has been agreed that the HGID estimate will be inputted at the cost change area (as tool go to be released by tomorrow).
2. Actual merit will be discussed during V3 cost correlation.
3. Also for future, we have requested QD / HGID members to route the CRF through New Model team for better communication and coordination.
4. Revised CRF will be sent by HGID team (Mayank San / Takumi Takahashi San).
This is for your information and further action please.
revert in case of any further clarifications.