・ Because tenant owner is still planning , we cannot order some equipments.
・ Because power meter is an imported products from Slovenia , it is difficult to improve delivery times.
・ We already informed PT.TAISEI about our proposed schedule.
・ We consider to unify the same colour of covered wire. but we need to order from the same supplier.
・ Power meter needs to read two time zone. But contract design is not given consideration to it yet.
・ There is not enough c-channel in the contract quotation.
・ There is not enough the cost of LP panel budget in the contract quotation.
・ There is not a remote microphone and a cabinet rack in the contract quotation.
・ In the contract quotation, worker & staff salary budget still using old data and has not been updated.