Advance Work Accomplishment Report:
1. Almost finish pouring of concrete for the beams as seen in picture one beam is remaining schedule to be finish today. Thanks to Laura Joan Matheu for the sands donated (hurot naman gud ang bas salamt sa donasyon).
2. Bought already angle bars and square bar for the steel rafter which supports the roofing.
3. Modern welding machine courtesy of Gutierrez Family thank you for the replacement of the old machine.
Next week schedule is the fabrication of the steel rafter which supports the roof.....Fabrication is leaded by Archt. Herman Sanchez and of course with the President Bernard Gonzales Angulo Jr. with yours truly and help from All Members.
With the help of the Almighty God the Project is Almost there....
Keep the spirit!!!!
Thank you for your support!
FYI see attach pix
Happy Weekend @ the Beach!!!!