Dear ALL
Good day to you.
Thank you for always doing business with us.
I submit an estimate when I used marine transportation.
We accept the shipment by sea according to the conditions of your order.
( PO#16001084 / FOB By Sea)
The Chiba factory has many orders and is a state beyond the tolerance level.
Due to the factory’s huge backlog of orders, the delivery date is still uncertain.
They say will definitely prioritize your order,
In the past the delivery date will be 1 month after the order is received.
However, it will now take 6 weeks.
I will do all I can within my power to negotiate to shorten the process,
and have it deliver earlier.
For now, it is estimated to receive a reply for the quotation on 6th October.
Please confirm. Thank you.